Short answer: an acceptance test is the witnessed, start-to-finish test of a new or substantially modified fire alarm system, performed by the installing contractor in front of the fire marshal's inspector before the system is approved for use. In Albuquerque it is scheduled through Albuquerque Fire Rescue's Plan Review, it follows the approved plans and NFPA 72's acceptance-testing requirements, and it ends with a signed record of completion that becomes the first document in the building's inspection history.
Before the test: plans, permit and checklist
Nothing gets tested until it has been reviewed. Albuquerque Fire Rescue publishes a fire alarm plan checklist for submittals: the designing contractor provides NICET III credentials with license number and signature or a fire protection engineer's seal, the installing contractor provides a copy of its State Fire Marshal Certificate of Fitness, the drawings show device locations and wiring, battery calculations prove 24 hours of standby power, manufacturer cut sheets carry model numbers and listings, and monitored systems show two separate transmission paths such as IP and cellular (Albuquerque Fire Rescue, Fire Marshal's Office: Fire Alarm Checklist). The city issues a fire alarm construction permit with a fee scheduled by protected area; the current schedule is on the Fire Marshal's Office pages. Statewide, 10.25.5 NMAC puts plan review and inspection of fire protection systems with the State Fire Marshal or the local fire marshal, as appropriate, so outside Albuquerque the same sequence runs through the local fire department's prevention division or the state office (New Mexico DHSEM, Office of the State Fire Marshal: 10.25.5 NMAC, Fire Prevention and Public Occupancy (2021 International Fire Code)). In unincorporated Bernalillo County, fire alarm construction documents also carry a New Mexico licensed fire protection engineer's review seal (Bernalillo County: ordinance adopting the 2021 International Fire Code (§901.6 inspection, testing and tagging)).
What happens on test day
The inspector witnesses the installing contractor operate the complete system against the approved drawings. Every initiating device is activated: each smoke detector with test smoke or aerosol, each heat detector with heat, each pull station, waterflow switch, duct detector and supervisory switch. Every notification appliance is checked for sound level and strobe coverage in the rooms it serves. The panel is put through its trouble conditions, the standby batteries carry the system through a power-loss test, and the signals are confirmed at the monitoring center on both transmission paths. Interfaces are exercised too: elevator recall, HVAC shutdown, magnetic door holders, and access-controlled doors that must release on alarm. NFPA 72 Chapter 14 governs the acceptance test as well as the ongoing inspections, and the contractor documents every device and result on a record of completion that the owner, the contractor and the inspector keep (National Fire Protection Association (NFPA): smoke detector inspection, testing and maintenance under NFPA 72 Chapter 14).
Who must perform it
The installing contractor must hold a State Fire Marshal Certificate of Fitness in the fire alarm discipline: under 10.25.2 NMAC nobody may install, inspect, maintain, service, tag or repair a fire alarm system in New Mexico without one (New Mexico DHSEM, Office of the State Fire Marshal: 10.25.2 NMAC, Certificate of Fitness rule). Thompson Security's fire alarm work runs under Certificate of Fitness #25-0242, and our designs are prepared by our NICET-certified fire alarm designers, Darrell Uher and John Martinez, or sealed by a licensed fire protection engineer.
After acceptance
Acceptance is the start of the maintenance obligation, not the end of the project. The IFC requires the system to be kept in operative condition and inspected, tested and maintained on the NFPA 72 schedule, and Albuquerque Fire Rescue inspects commercial buildings annually and asks for those records (Albuquerque Fire Rescue, Fire Marshal's Office: annual fire inspections). Keep the record of completion, the approved drawings and the cut sheets for the life of the installation; they are the baseline every future inspector compares against. Our monitoring and service agreements schedule the first annual inspection from the acceptance date, so the record never lapses.
Common reasons an acceptance test fails
A strobe hidden by a partition wall added after the drawings were approved; a detector mounted too close to a supply-air diffuser; a pull station mounted outside the accessible reach range; battery calculations that ignored a later device addition; one transmission path instead of two; a panel programmed with device labels that do not match the drawings. Each of these means a return visit and a second inspection. A pre-test by the contractor the day before, walking the building with the drawings in hand, catches almost all of them, and it is standard practice on every Thompson installation.